Vacation Request System
Hi, We need to work on every Sat. So i need to count + 0.5 day on Sat. Please help where can i change the calculation for Days Left and other rules are same. I try to add the following simple formula at "Duration", but it wont show Sat at Leave Calendar View and the final Day Left seems not correct. @If(@IsNewDoc; 1; @Success); @BusinessDays(StartDate; Return; 1:7 ;@DbLookup("":"NoCache";"";"Holidays";Country;2))+ (@BusinessDays(StartDate; Return; 1:2:3:4:5:6 ;@DbLookup("":"NoCache";"";"Holidays";Country;2))/2) Thanks Janny
I have the same problem. Did you solve this problem
Hi Fatih, Thank you for your interest in Vacation Request! Weekend days, or lack there of, can now be set in the location documents. For each of your locations set the weekend days to not include Saturday. HTH, Bob